One grid, joints that undo, walls in layers.

Opentecture is an open system of building parts on a 40 mm grid. Parts bolt, clip and gasket together, so a wall comes apart without damage. This page explains how, and says plainly how sure we are of each piece.

4 cm grid · Reversible joints · Open source

1 · The grid is the contract

Every part, hole and joint lands on a 40 mm (1⅝ in) grid. Connection points sit at the grid intersections. Parts from different makers fit because the grid says so, not because they came from us.

Parts are named by function, then size in grid units. A Wall cassette 30 × 60 is 30 by 60 grid units: 1.2 × 2.4 m (4 × 8 ft).

The 4 cm grid comes from OpenStructures, Thomas Lommée's open modular standard. Standard materials join the grid through adapters: a bracket with grid holes on one side and a clamp on the other. A 2 × 4 stud, a run of conduit or a pipe can all join the system without being cut to fit it.

2 · Joints over glue

If it can't come apart, it isn't finished. Opentecture uses three kinds of joint, and no adhesive.

Bolts
Structure fastens through grid holes at connectors and nodes. A bolt comes out as cleanly as it went in, and the hole is still on the grid for the next part.
Clips
Finishes and light parts clip on. Taking a panel off for access is a minute's work, not a repair.
Hard-stop gaskets
Seams seal with an EPDM bulb that compresses to a fixed stop. The stop sets the squeeze, so the seal is the same the fiftieth time the wall goes back as the first.

No cutting on site. Every part arrives at its size, and leaves at its size.

3 · The wall as layers

A stick-built wall bonds structure, insulation, wiring and finish into one thing, so changing any of them means opening all of them. An Opentecture wall keeps each job in its own layer, so each one can change on its own schedule. This follows John Habraken's idea of supports and infill: separate what lasts from what changes.

  1. Structure

    Plywood ribs on the grid carry the load. This is the layer that lasts longest, and the one you touch least.

  2. Cartridge insulation

    Mineral wool in a sleeve that carries its own seal. The cartridge travels and gets reused with the wall, and swaps for a better one without touching the structure or the services.

  3. Service cavity

    A cavity on the room side, one grid unit deep, carries wiring and pipes. Adding an outlet means opening a panel, not a wall.

  4. Clip-on finish

    Interior panels clip over the service cavity, and rainscreen boards hang outside. Finishes change with taste, and nothing behind them has to.

4 · Assembly order

Here is our planned sequence for a two-bedroom home. The parts are made off site while the permit is reviewed, so the site sees a kit, not a lumber yard.

  1. Configure the home from the part library and survey the site.
  2. While the permit is reviewed, fabricate the parts off site: CNC-cut panels, brackets, and a wet-core module that holds the kitchen and bathroom plumbing as one unit.
  3. Set ground screws and a ring beam. There is no slab to pour and no week of curing.
  4. Assemble the floor cassettes into a chassis on the ring beam.
  5. Set the gasketed wall cassettes, then the roof cassettes and roofing.
  6. Lower the wet-core module into place.
  7. Pull wiring and connect plumbing in the open service cavities, then pass the rough-in and air-seal inspections.
  8. Clip on the interior finish panels and hang the rainscreen boards.
  9. Lay flooring, fit fixtures and devices, then final inspection and keys.

Our plan puts this at 31 days on site, against 82 for the same home stick-built. That number is a hypothesis. It assumes the joints work as designed, which the rigs below test first.

5 · How sure we are

We label every claim with one of four words: hypothesis, prototype, tested, in service. Today the part library, the model house and the build sheets exist in software. No physical part has been tested yet, so every physical claim below is a hypothesis.

Claim Status How we'll know
Cartridge insulation matches a standard batt. hypothesis Rig 1, a cooler hot-box, about $340.
A hard-stop gasket still seals after 50 cycles. hypothesis Rig 2, a seam rig measuring airflow at 50 Pa after 1, 10 and 50 cycles.
The joint and the grid, not panel mass, set sound and heat loss. hypothesis Rig 3, one wall bay at full size.
Parts from different makers fit on the grid. hypothesis The first parts made by two different shops.
31 days on site for a two-bedroom home. hypothesis A pilot build, timed.
At volume, slightly under stick-built all-in, mostly from fewer days on site. hypothesis Supplier quotes, sourced labour rates and a pilot build.

Results land in the design notebook with dates. When a claim changes status, this table changes with it.